SLATE RUN ROAD UPDATE: Road Base Stabilization Continues

Base Stabilization nearing Completion.png

Crews will perform additional base stabilization to Slate Run Road tomorrow and Friday, and aim to lay pavement in affected areas by the end of the day Friday. Once the base stabilization is complete, crews can then level the roadway and begin laying final pavement over the next few weeks.

The Slate Run Road Project aims to bring improved drainage and stormwater systems to the neighborhood, curbs and gutters, new sidewalks, and an improved roadway. As the project progressed, crews encountered poor soil conditions underneath the roadway. The city consulted with a local geotechnical engineering firm to determine the best course of action to ensure a long-term, stable roadway. The recommended base stabilization work is being completed over the next two days.

We appreciate your patience and understanding as we complete this important infrastructure project.