Grant Line Road Project Prep Work Underway

Grant Line Road Project Prep Work.jpg

The Grant Line Road Project will run from Daisy Lane to McDonald Lane and will include multiple infrastructure and safety improvements. The multi-use path on the west side will be extended from Cherokee Drive to Beechwod Avenue, and sidewalks will be added on the east side. Additional drainage improvements will be made, including new curbs and gutters, drainage inlets, and a new storm-sewer system.

A new left-turn lane (southbound) will be added at Jollisaint Avenue.  Additionally, new ADA compliant sidewalks, ramps, pedestrian signals, and traffic signals will be added throughout the project area.

Multiple efforts are underway in advance of the upcoming Grant Line Road Project.

Dan Christiani Excavating will be performing a Water Main Repair on Grant Line Road (near Beechwood Avenue) starting tomorrow, Wednesday June 20th. This work will require a lane closure while crews work to repair this infrastructure.

Work is also underway preparing for utilities to relocate in anticipation of the Grant Line Road Project. Rolling lane closures from Daisy Lane to McDonald Lane on Grant Line Road are anticipated while crews work on this part of the project. Flaggers and other safety personnel and equipment will be on-site to assist with traffic during the lane closures.