Grant Line Road Contractor Fined $3000 Per Day for Missed Schedule

Grant Line Road.png

The contractor completing the Grant Line Road Improvement Project is currently being fined by the city $3000 per day for failing to meet the scheduled completion date.

The contractual date for completion of the project was June 18, 2019. Beginning June 19, the city has fined the contractor $3000 per day for failing to complete the project, per contractual agreements. Starting August 18th, if the project is still not completed, fines are increased to $5000/day.

Since these fines have been initiated, the city has seen increased activity from the contractor and crews along Grant Line Road.

“We will continue to insist on a timely completion of the work, and ensure that the work is of the highest quality,” stated Mayor Jeff Gahan.